View gantt chart in ms project

broken image

To make sure each subproject of a master project is on time. But you might need to see more than one for a couple reasons: You can set up your project schedule to display as many critical paths as you need to keep tabs on your project.Ĭhoose Advanced, scroll down to the bottom, and then select Calculate multiple critical paths.Ĭhoose Format, and then select Critical tasks.īy default, Project shows only one critical path, the one that affects the project’s finish date. But you can tell Project to include tasks with one or more days of slack on the critical path so you can see potential problems coming from farther away.Ĭhoose Advanced, and then scroll down to the Calculation options for this project area.Īdd a number to the Tasks are critical if slack is less than or equal to box. Change what tasks show up on the critical path That is, it only applies to the master project you’re working on. Tip: This setting does not affect other projects.

broken image